08/31/03 The Home Front.                                       Back Side View.
White Tail Ridge Estates, Grand Rapids, MN.

SOLD!
Walking distance to county fairgrounds; within a few miles of elementary school, middle school, high school, sports complex, performing arts center and downtown!
DIRECTIONS...

09/12/03. Landscaping: Rock wall in place, grass seed spread, culvert installed under driveway (and worked well amidst this week's rain)!

09/01/03. Septic system has been inspected, approved and covered. Finishing touches inside and out are in progress.

08/14/03. So much is now completed including the NAREC's Open House! Contact Lee or Shannon, NAREC, and come and see for yourself!

08/03/03. Well is in. Ceramic tiling complete. Laminate flooring in progress.

07/18/03. Most light fixtures are installed. Inside doors are installed. Inside trimwork in progress.

07/12/03. Garage doors and bathroom flooring installed. Inside trimwork  is being stained.

06/30/03. Electric Power is ON. Siding is over 90% complete.

06/20/03. Siding is 75% complete. Kitchen cabinets to be installed next week.

06/17/03. Siding still in progress. Indoor painting in progress.

06/06/03. Exterior cedar siding started (smells so good). Small rock wall on east side of garage built. Ceilings textured; Drywall/Taping complete.

05/31/03. Ceiling insulation complete; Stucco around foundation complete. Taping in-progress.

05/24/03. Concrete garage floor (heated) and entryway sidewalk complete. Entry doors installed. Wall Insulation complete. Sheetrock installed.

05/14/03. Electrical rough-in passed inspection. Gas Fireplace and Windows installed. Roofing complete; Tyvek complete; Outside Masonry complete.

05/09/03. Roofing almost complete. Too bad it rained today. Masonry, Tyvek, Plumbing, Electrical in-progress. Windows next week.

04/25/03. Roofing in-progress.

04/18/03. Framing on both floors is almost complete.

04/04/03. Framing-in of the walls is proceeding. First floor is framed; second floor and rafters in-progress.

03/14/03. The heated slab foundation is poured!

Home Plan. Link to AMDA.Home plan by Alan Mascord Design Associates