| 12/22/07 | We love showing off this house but we're selling! |
| 10/9/06
|
NMBA Showcase of Homes Tour was a success! The green grass shown
through the autumn leaves scattered everywhere and the view of the lake
was lovely!
|
| 6/30/06 | Finishing garage interior walls. Rock retaining wall built in front. |
| 4/26/06 | Preparing for Open House on Saturday, Apr 29,10 am - 5 pm and Sunday April 30, 1 - 5 pm |
| 2/23/06 | Great Room's main light fixture and kitchen lighting installed. Lots of details completed. Looking good! |
| 12/05/05 | Adjustable electric in-floor heat makes for toasty toes under ceramic tile in both main floor bathrooms. Gas fireplace works great! Wall ceramic tile in master bath, around tub, complete. |
| 11/09/05 | All carpeting installed: master and guest bedrooms. All real wood laminate flooring installed: great room. Ceramic tile flooring complete today: remainder of upstairs flooring. |
| 11/06/05 | Carpet installed in guest bedroom. Ceramic tile flooring being installed in garage/front entryway, "guest hallway", and master bathroom. Pressure tank is installed. County septic inspection complete and approved. |
| 10/29/05 | Unique woodwork above fireplace mantel and living room lakeside windows. Unique ash railing around staircase. Real hardwood laminate flooring installation is in-progress. Gas fireplace is working. Window and door trimwork complete. Rock retaining wall near lakeside walk-out is built. |
| 10/04/05 | Beautiful kitchen countertop! Ceiling insulation nearly complete. Door and window trimwork installation in-progress. |
| 9/17/05 | "Chestnut" Oak kitchen cabinets are being installed and walls are being painted Anitique White. |
| 9/02/05 | Septic tank is in. Gas fireplace is being installed. Light fixtures are awaiting hook-up. |
| 8/18/05 | Ceilings are sprayed and wall priming/painting is in-process. |
| 8/09/05 | Drywall is up. |
| 7/19/05 | Exterior siding is complete. Interior drywall and mudding in-progress. Well is in-progress. |
| 6/24/05 | Downstairs windows are installed. Tyvek up. Exterior siding is in progress. Well permit is purchased. |
| 6/06/05 | Lower level concrete floor is poured. Electrical & Plumbing/Heat&AC subcontractors are hard at work. |
| 5/27/05 | Windows & sliding glass door are installed upstairs. Garage concrete floor is poured. |